Evaluation scheme for underground cables vs. overhead lines

Year

2013

Organisation

Swissgrid

Description

Whether transmission lines are to be constructed overhead or placed underground in Switzerland is being decided on a case-by-case basis and in accordance with objective criteria. For this purpose, the Swiss Federal Office of Energy (SFOE) has developed a "transmission lines evaluation model”.

 

Main information:

The main objective of the new model is to evaluate various options in order to define the most suitable corridor for transmission lines. At the same time, the question whether transmission lines should be placed overhead or underground can be answered and the licensing procedure can therefore be accelerated. The model comprises four pillars, each of which contains three or four groups of criteria (spatial development, technology, environment and the economy). Projects are examined and evaluated on the basis of the criteria. After initial findings have been obtained, minor adjustments will be made to the new model and a manual will then be prepared.

The application of this evaluation model to every new project is mandatory for Swissgrid. This model makes decisions more transparent and helps stakeholders understand which criteria were taken into account when coming up with the decision.

 

RGI gratefully acknowledges the EU LIFE funding support:

EU LIFE funding support Logo

Funded by the European Union. Views and opinions expressed are however those of the author(s) only and do not necessarily reflect those of the European Union or the LIFE Programme. Neither the European Union nor the granting authority can be held responsible for them.