Calendar 2017
Location Germany

Organisation: TenneT, TransnetBW

Innovative and transparent public participation in Germany’s central electricity grid project, SuedLink. The process, which was co-developed with local governments and other stakeholders, included various engagement formats, such as an online platform and info as well as landowner forums. 

Online participation 

Joint planning with local governments – co-developed concept for involving local communities and the public 

Special cooperation with the County Alliance „Hamelner Erklärung” 

Engaging 435 municipalities 

Information forums in all regions affected by the project 

In the further course of the approval process, more specific formats (e.g. on logistics) for stakeholders such as landowners or local municipalities 

Digital formats during the Corona pandemic 

Long before the start of the official permitting procedure, TransnetBW and TenneT presented possible underground cable corridors in the regions that could possibly be impacted by the project. With the help of a new communications and engagement approach based on openness, transparency and active participation, local knowledge was included into the planning. The public could view all recorded data and post comments via a web-based Geographic Information System (WebGIS) – it was the first time such a special online tool was created and used in a grid project in Germany. The comments received via the tool resulted in 3811 variations for SuedLink.  